    Which activities most deserves your immediate attention?
    AC=3000 EV=2900
    PV=3000 EV=2900
    AC=3000 EV=3200
    EV=3000 AC=2400

    What will the answer & why??
     
    #1
  2. Nishad Tupe

    Nishad Tupe Active Member
    Alumni

    Joined:
    Mar 23, 2016
    Messages:
    31
    Likes Received:
    0
    Great question, Thanks for posting ..I know this is from the exam answer is D as CV is highest. Initially, It did confuse me as well.
    I think the intent here is to see how far you are from the cost baseline (accepted budget for that time) so even if it is positive you need to see the immediate attention that did you miss any activity as AC is so less. Any changes to the baseline promote the changes to PM plan eventually.
     