Schedule Compression Question

Discussion in 'Project Management' started by FIROZ AHMAD, Sep 5, 2017.

  1. FIROZ AHMAD

    FIROZ AHMAD New Member

    Joined:
    Jul 29, 2017
    Messages:
    1
    Likes Received:
    0
    A project activity has the following values for the earliest and latest it can start and the earliest and latest it can be completed. An activity's Late Start (LS) is 5/day and Late Finish is (LF) 10/day. Similarly Early Start (ES) is 3/day and Early finish (EF) is 8/day. What is the float of this activity?
     