Search results

  1. G

    Clarification required

    1. While going through PMP questions, one of the options was that the approved change request needs to be returned to the CCB immediate as PM was not satisfied with the rejection of the change request. Can we do that? If yes, what can be the possible scenarios? If yes, can we send it for...
  2. G

    Part II :HELP REQUIRED FOR EXPLANATION ON QUES OF QUIZ 4

    Q75. During the project execution, a large number of changes are made to the project. The Project Manager should: Wait for all the changes to happen and print a new schedule Make only the changes approved by the management Talk to management before any changes are made Make the approved changes...
  3. G

    HELP REQUIRED FOR EXPLANATION ON QUES OF QUIZ 4

    Q40. You have been assigned as the Project Manager of a development project. The WBS has been completed and the activity sequencing has also been done. The activity duration estimate has also been received by each of the team members. What should be the next step in the project? Get cost...
  4. G

    HELP REQUIRED FOR EXPLANATION ON QUIZ QUES

    In my opinion, the sponsor is providing the money and he is asking to cut down the budget by 10%. As a PM we should discuss this new constraint with the team to find out if its possible and then provide the options to the sponsor. IMO, since the sponsor has asked for 10% cut, hence he already...
  5. G

    Clarification required on Change request

    The project manager observes that the team members are accepting a number of changes to the deliverables with little attention to ensuring the acceptable standards. When questioned, the team members reply that the changes are relatively minor. What part of the project management plan should the...
  6. G

    Clarification required

    Who determines the appropriate levels of accuracy and precision? A. The stakeholders. B. The Project manager C. The project management team D. The project sponsor As per me it should be stakeholders (customers) because it is 'Requirement' that how much accuracy and precision is...
  7. G

    HELP REQUIRED FOR EXPLANATION ON QUIZ QUES

    1. Simplilearn test No 2 Q No 14 You are managing a complex project which requires some highly skilled resources on embedded design. You obtain these resources from the organization pool. You specify the duration for which they would be required. Once your project activity is complete, you...