Another Q you are wrong. SPI .95 means behind the ...

Discussion in 'Other Project Management Courses' started by Narsima Rao, Feb 18, 2017.

  1. Narsima Rao

    Narsima Rao Member

    Joined:
    Jan 31, 2017
    Messages:
    4
    Likes Received:
    0
    Another Q you are wrong. SPI .95 means behind the schedule. you said 'c' is the right answer, telling ahead of schedule. like this so many mistakes really.

    You are reviewing the current work performance report from the team during your weekly meeting. You have a contingency plan with a predetermined risk trigger for the SPI of .95. The current BCWP is $175,000, and the BCWS is $170,000. What should you do first?

    a. Look for ways to crash the schedule and get it under control.
    b. Determine the root cause of this negative index.
    c. Nothing at all because the SPI indicates the project is ahead of schedule.
    d. Contact the sponsor and tell him the project is behind schedule but you are working on it.
     
    #1
  2. Ambika_2

    Ambika_2 Well-Known Member
    Simplilearn Support

    Joined:
    Nov 25, 2015
    Messages:
    217
    Likes Received:
    8
    Hi Narsima,

    Thank for sharing your update on the content. We have noted your point and have shared the feedback with our content team.
    We would evaluate the same and try to update the contents accordingly.

    Regards,

    Ambika
    GTA-Simplilearn
     