Help for FF and FS & lag and Lead question

Discussion in 'PMP' started by Mamta jain, Aug 8, 2019.

  1. Mamta jain

    Mamta jain Member

    Joined:
    Aug 4, 2017
    Messages:
    5
    Likes Received:
    0
    I need help to understand below question, how to apply FF -2 days and FS + 3 days

    Activity 1 has a duration of 20 days, activity 2 of 10 days, activity 3 of 5 days and activity 4 of 6 days.
    [​IMG]

    What is the minimum total duration between the milestones A and B?

    37 Days
    36 Days
    39 Days
    42 Days
     
    #1