    In one of the mock tests, there is this question (to be exact, there is no question at all):

    "
    You are examining the network paths for your project. Path A's duration is : 1-2-3-5-8)

    SELECT THE CORRECT ANSWER
    A. Path B's duration is 1-3-5-6-7
    B. Path C
    C. Path B
    D. Path A
    "

    What kind of question is this? and what's the answer?
     
    #1
  2. tim jerome

    tim jerome Well-Known Member
    Trainer

    Joined:
    May 15, 2015
    Messages:
    1,981
    Likes Received:
    563
    It's question 37 in exam 3 - here's the question:

    You are examining the network paths for your project. Path A's duration is: 1-2-3-5-8; Path B's duration is 1-3-5-6-7; Path C's duration is 1-2-5-4-9; and Path D's duration is 2-3-4-4-8. Which of the following is the critical path for this project?

    Path D
    Path C
    Path B
    Path A

    Something has broken between the data and your course console; please contact support.

    p.s. What's the answer now? (grin)
     
    #2
    _38657 likes this.
  3. _38657

    _38657 Member

    Joined:
    Aug 28, 2018
    Messages:
    4
    Likes Received:
    0
    I was wondering too? Can you please elaborate
     
    #3
  4. tim jerome

    tim jerome Well-Known Member
    Trainer

    Joined:
    May 15, 2015
    Messages:
    1,981
    Likes Received:
    563
    There seem to be a few questions in the simulation test papers that have broken linkages; I provided the question above as it should read.

    Are you able to determine the answer now? If you wish me to dissect and provide the answer, please say so - however, it's good practice to try the answer first.

    I'll continue to look for comments on this thread.
     
    #4
  5. _19820

    _19820 Member

    Joined:
    Jan 8, 2018
    Messages:
    3
    Likes Received:
    0
    Hi Tim, I am still unable to determine the CP as I cannot find any durations nor logical way to compare the paths. Are we supposed to be able to answer this without any duration info? Thanks
     
    #5
  6. tim jerome

    tim jerome Well-Known Member
    Trainer

    Joined:
    May 15, 2015
    Messages:
    1,981
    Likes Received:
    563
    If you look at the question in the top, you observe the durations are missing from B,C, and D. I went back to the original question and found them.

    What makes a critical path critical? The fact that it has the longer duration. You can determine the solution from this understanding.
     
    #6
  7. _49203

    _49203 Active Member

    Joined:
    Nov 22, 2018
    Messages:
    36
    Likes Received:
    5
    I believe the answer is B? 22 is the longest duration = critical path.....
     
    #7
  8. tim jerome

    tim jerome Well-Known Member
    Trainer

    Joined:
    May 15, 2015
    Messages:
    1,981
    Likes Received:
    563
    B is correct. Unless otherwise stated, assume all F-S relationships, no leads, no lags. We're comparing simple sums.
     