How to calculate Total Float and Free Float?

Discussion in 'Simplilearn Support' started by Asheesh Patel, Feb 26, 2015.

  1. Hi all,

    How to determine the Total Float and Free Float calculation?

    How is an activity float calculation done?

    Is there any formula? Is it the sum of all the Free Floats?

    I am confused regarding the difference between Free Float & Total Float.

    Any help?

    Regards,

    A. Patel
     
    #1
  2. MukeshShende

    MukeshShende Member
    Alumni

    Joined:
    Feb 18, 2015
    Messages:
    11
    Likes Received:
    15
    #2
    Shruti likes this.
  3. Om Prakash Bang

    Om Prakash Bang Well-Known Member
    Alumni

    Joined:
    Feb 18, 2015
    Messages:
    92
    Likes Received:
    39
    Total Float is the amount of time activity can be delayed without delaying the project end date where as Free Float is without delaying the early start date of its successor(s). In the former next successor(s) early start can be changed. As mentioned by Mukesh, try drawing network diagram, identify critical path, near critical path and other path and perform float calculation on different path to get comfortable. Activities on the critical path have ZERO float.
     
    #3
    Shruti likes this.
  4. Thank You Mukesh Sir and Om Sir. The answers and the link helped me to clarify the difference.
    Mukesh Sir - I have read your blog few weeks back as well. They are very informative.

    So what I read and understood clearly was -

    Total Float (slack) = (LF date – ES date) OR (LF date – EF date)
    Free Float = (ES of next Activity – EF of current Activity)

    ES = Early Start and EF = Early Finish
    LS = Late Start and LF = Late Finish

    Thanks
    A. Patel
     