Issue log inout and output?

Discussion in 'PMP' started by _34920, Nov 3, 2019.

  1. _34920

    _34920 Member

    Joined:
    Jul 17, 2018
    Messages:
    4
    Likes Received:
    0
    @ Tim...Which of the following is NOT an input to the process Manage stakeholder engagements?
    SELECT THE CORRECT ANSWER

    Stakeholder Management Plan
    Communication Management Plan
    Change Log
    Issue Log
    Correct Option:D

    EXPLANATION

    An issue log is the output of the process Manage stakeholder engagements. All the other options are inputs to the process.

    If you read PMBOK, it says issue log is both input and output for Manage Stakeholder Engagement Plan. I am confused with this answer.
     
    #1
    Last edited: Nov 4, 2019
  2. tim jerome

    tim jerome Well-Known Member
    Trainer

    Joined:
    May 15, 2015
    Messages:
    1,915
    Likes Received:
    553
    You are correct. This question was not updated with the release of the 6th edition; thanks for bringing this to our attention.

    At the same time, this is a unique opportunity - we use our issue logs in engaging our stakeholders, and when we engage them, it provides us an opportunity to capture new issues.
     
    #2
  3. _34920

    _34920 Member

    Joined:
    Jul 17, 2018
    Messages:
    4
    Likes Received:
    0
    Thanks for the clarification.
     