    A project manager is in the process of developing a detailed description of a project by identifying project deliverables and work required to create those deliverables. Which of the following will NOT be an input to this process?
    SELECT THE CORRECT ANSWER

    Enterprise environmental factors
    Project charter
    Requirements documentation
    Organizational process assets

    Simplilearn states that answer is C. However Requirements Doc is an input to Define Scope as per PMBOK 6th. I got confused with these choices....
     
    #1
    Ariel Achtman likes this.
  2. Ariel Achtman

    Ariel Achtman Member

    Joined:
    Feb 20, 2018
    Messages:
    4
    Likes Received:
    0
    Bumping this question, as I am also interested in the answer.
     
    #2
  3. tim jerome

    tim jerome Well-Known Member
    Trainer

    Joined:
    May 15, 2015
    Messages:
    1,935
    Likes Received:
    553
    I've discussed this question a few times on this thread.

    The process Define Scope has all of these as an input. This has been raised a few times. I can't remember, but I think this is a change from the 5th edition, and this question has not been updated.

    Thanks again for all your input.
     