PMP Network Diagram

Discussion in 'PMP' started by Girish Venkatesh, Sep 26, 2016.

  1. Girish Venkatesh

    Alumni

    Joined:
    Jul 5, 2016
    Messages:
    2
    Likes Received:
    0
    List Days Predecessor
    Activity A 5 A and F are Parallel
    Activity B 7 A
    Activity C 9 B
    Activity D 3 C
    Activity E 1 D
    Activity F 1 A and F are Parallel
    Activity G 10 F
    Activity H 5 G
    Activity X 11 F

    I have few questions, need your help on that please...
    what is the earliest date Task H can start?
    what is the earliest date Task H can finish?
    what will be the float on Task G?
    what is the latest finish date of Task F?

    Thank you
    Girish Venkatesh
     
    #1
  2. Praveen Kumar Nomula

    Alumni

    Joined:
    Jul 31, 2016
    Messages:
    4
    Likes Received:
    0
    Based on my understanding below is answers to your queries, Can you confirm are these correct? or someone from trainer need to validate it:

    Earliest task H can start : 11
    Earliest task H can finish: 16

    Float on Task G : 9
    Latest finish of Task F :10
     
    #2
  3. Girish Venkatesh

    Alumni

    Joined:
    Jul 5, 2016
    Messages:
    2
    Likes Received:
    0
    Hey Praveen,

    Thank you for this. Please find below reply.
    Earliest task H can start : 11 - This is actually 12 due to activity X
    Earliest task H can finish: 16 - This is Actually 17 due to Activity X again

    Please advise how did you get the following.. Attached file shows the Network diagram
    Float on Task G : 9
    Latest finish of Task F :10

    Br,
    Girish Venkatesh
     

    Attached Files:

    • ND.PNG
      ND.PNG
      File size:
      67.7 KB
      Views:
      6
    #3
  4. Praveen Kumar Nomula

    Alumni

    Joined:
    Jul 31, 2016
    Messages:
    4
    Likes Received:
    0
    Hi Girish,

    My network diagram and yours is almost matching, but can you check X in your diagram, I think X directly go to finish and as per you successor of X is H, but this is not mentioned in the table.
     

    Attached Files:

    • ND.jpg
      ND.jpg
      File size:
      48.3 KB
      Views:
      5
    #4
  5. Sreidhar D(1820)

    Sreidhar D(1820) Well-Known Member
    Alumni

    Joined:
    Sep 28, 2012
    Messages:
    84
    Likes Received:
    16
    Hi Girish
    Hope you have started your preparations for the exam.
    Sridhar.D
     