PMP Simulation Question #Bala

To acquire and manage the project team, which of the following plan or documents should be referred to?
SELECT THE CORRECT ANSWER

Human Resource management plan
Procurement management plan
Project charter
Resource management plan and Procurement management plan
Correct Option:D

Explanation

According to the new examination content outline, a resource management plan should be considered in addition to the procurement management plan.

Please explain why Procurement management to manage Resource
 