    Question: A hospital is installing a new management system to computerize the hospital functions. For this purpose, representatives from several departments are selected to create a task force assigned to implement the project. This organization structure is called:

    Answer: Composite Organization

    There is a choice of "Projectized Organization". When I learned in the lesson, it seems like that the Projectized Organization is the same as Composite Organization. Even in PMBOK, it describes in such a manner.

    Why this answer is Composite Organization?
    What is the difference between Composite Organization and Projectized Organization?
     
    #1
  2. SRINIVASA RAO RUSUM

    Joined:
    Jun 11, 2020
    Messages:
    2
    Likes Received:
    0
    A projectized organization works by arranging their activities into portfolios or programs and execute them through projects. In these type of structures, the project manager is the final authority over the project they are handling. The team that is working on the project reports solely to them.
    A composite organization blends the functional, matrix, and projectized types of organizations. A composite is just two or more models that are adapted for a special project, for simplicity, or to keep power in check. Most modern businesses are of the composite type.
    https://www.simplilearn.com/types-o...nization blends the,are of the composite type.
     