    Q:Your project colleague is confused about network diagrams. Specifically, he wants to know the significance of the critical path in a network diagram. What would you tell him?

    A:The critical path is the longest path with the shortest duration to complete the project with zero total float on the network

    This seems incorrect as the Critical Path is the longest path but not the shortest duration necessarily? Clarification will be appreciated
     
    #1
  2. B K S Prasad

    B K S Prasad Well-Known Member
    Simplilearn Support Alumni Trainer

    Joined:
    May 26, 2011
    Messages:
    204
    Likes Received:
    49
    Shortest duration means minimum time that is required to complete the project which is nothing but the duration of the project.
     