    Q: Your contract states that the maximum charge for services from the seller will be $50,000/month, however, the actual invoices have been $100,000 for the last three months. Stopping the seller's service will impact the project schedule. Under these circumstances, the best thing to do is to revirew the:

    A. Contract Change control system
    B. Scope Control System
    C. Performance reporting system
    D. Cost Change Control System

    Correct Answer A

    Why not C? Most probably we have an issue of performance that cause the overrun of cost
     