    Hi @tim jerome-

    why is option A incorrect? Isn't the list of risk responses an output of the Plan Risk Response process? The Identify risks process generates the risk register/risk report, which are later updated thru the response planning process? Thank you very much in advance.

    What are the primary outputs from the identify risks process?

    List of identified risks
    List of risk responses
    Both of these
    Neither of these
    Correct Option:C

    Explanation

    Both of these. Both the list of identified risks and potential responses are the two primary outputs of the identify risks process.
     
    #1
    Last edited: Aug 2, 2019
  2. _38317

    _38317 Member

    Joined:
    Aug 24, 2018
    Messages:
    3
    Likes Received:
    0
    #2
  3. Arvind Shekhar

    Arvind Shekhar Well-Known Member

    Joined:
    Mar 21, 2018
    Messages:
    199
    Likes Received:
    71
    Hi
    Option A is correct answer. (NOT INCORRECT)
    Option B is also a Correct answer.(NOT INCORRECT)
    Option A and B Both are correct answer, that's option C
    Option D can't be a right answer as option A and option B both are primary outputs of Identify risk process.
    here you have to choose only one best ( more correct ) answer that is C . it covers both correct options.
     