simulation test 7

Discussion in 'PMP' started by AS12345, Aug 2, 2019.

  1. AS12345

    AS12345 Well-Known Member

    Joined:
    May 10, 2019
    Messages:
    76
    Likes Received:
    12
    You are in charge of a project to build a bridge across a river. You are midway through the project. However, due to changes in environmental laws, the project can no longer proceed and would need to be terminated. Executive management has asked you to document the level of work completed for the project. In which of the following processes would this be done?
    SELECT THE CORRECT ANSWER

    Project Closure
    Contract closure
    Project charter
    Scope Verification
    Correct Option:D

    EXPLANATION

    Scope verification is performed not only while a project is being executed but it is also performed when a project is terminated. It is used to determine the level of completion.

    @tim jerome can you please help understand .
    In this question-scope verification means verifying quality and when the project is terminated arent we supposed to go to close project /phase process.

    Regards
    Archana
     
    #1
  2. _49203

    _49203 Active Member

    Joined:
    Nov 22, 2018
    Messages:
    36
    Likes Received:
    5
    +Following.....
     
    #2
  3. Arvind Shekhar

    Arvind Shekhar Well-Known Member

    Joined:
    Mar 21, 2018
    Messages:
    201
    Likes Received:
    71
    Please look at options given there and question statement , Project terminated, management want to know out of given scope how much work has been completed.
    you are right we are closing project.
    except option C (Project charter ) all other are related to and part of Close project or phase. Scope verification , contract closure, project closure in that order.
    Now statement says you are asked to document level of work completed .
    How ? verify scope it will be easy way to know what is complete and what is not complete. verification of quantum of work completed.( I presume you intended to say quantity instead of quality)
    To fulfill task given by management verification of Scope best answer.
     
    #3
    AS12345 likes this.
  4. AS12345

    AS12345 Well-Known Member

    Joined:
    May 10, 2019
    Messages:
    76
    Likes Received:
    12
    Thanks Arvind!
    In a rush to answer am missing few keywords.

    Archana
     
    #4

Share This Page