Tim - Question on Project Selection

Discussion in 'PMP' started by _51292, Mar 26, 2020 at 6:03 PM.

  1. _51292

    _51292 Active Member

    Joined:
    Dec 9, 2018
    Messages:
    18
    Likes Received:
    0
    Q: Project X: Payback period 12 months and NPV is 350, Project Y: payback period 24 month and NPV 400

    A: Project Y because the NPV is higher
    B: Project X because payback period is shorter
    C: Can not be determined based on provided information
    D: Project X because NPV is positive and Payback is shorter

    Correct Answer is C, why not A ?
     