Trick question

Discussion in 'PMP' started by _49203, Aug 15, 2019 at 1:13 PM.

  1. _49203

    _49203 Active Member

    Joined:
    Nov 22, 2018
    Messages:
    32
    Likes Received:
    3
    Please help me understand why options A or D are incorrect? A,B, and D all seem plausible, so why B?

    A - He is also going through the influence of risks on project objectives => Manage risks?
    D - He is collecting information on cost, schedule, and level of quality =? Monitoring and controlling?


    A project manager in an MNC corporation is in the process of collecting, organizing, and disseminating information on how project resources are being used to complete project objectives. In addition, he is collecting information on cost, schedule, and level of quality. He is also going through the influence of risks on project objectives. Which process is the project manager in?

    Direct and Manage Project Work
    Manage Communications
    Earned Value Technique
    Monitor and Control Project work
    Correct Option:B
     
    #1

Share This Page