    A customer, in the later part of project execution, wants to add scope to the project. Tom, the project manager, discusses this change with the customer and raises a written change request. He then evaluates if this change can be addressed through project reserves and explores alternatives. He finds that this addition would result in missing the next milestone delivery. What should he do NEXT?
    SELECT THE CORRECT ANSWER

    A.Evaluate the impact of the change on other factors of triple constraint - cost and time
    B.Perform Integrated Change Control
    C.Get an approval from the Change Control Board
    D.Update the project baseline and inform the customer
     
    #1
  2. Sahil Mahajan_1

    Sahil Mahajan_1 Well-Known Member

    Joined:
    Apr 3, 2019
    Messages:
    65
    Likes Received:
    17
    @Moderator, could this be looked into please?
     
    #2
  3. tim jerome

    tim jerome Well-Known Member
    Trainer

    Joined:
    May 15, 2015
    Messages:
    1,846
    Likes Received:
    535
    A comes before C, which comes before D. B is actually all this together, so it's one of these items.

    Where are we in this sequence? IT seems we've analyzed impact from the triple constraint (look to the 'missed the next milestone delivery), so I'd opt to submitting it to CCB before updating the baseline and informing the customer. C seems to be the right answer.
     
    #3
    Sahil Mahajan_1 and AS12345 like this.
  4. Sahil Mahajan_1

    Sahil Mahajan_1 Well-Known Member

    Joined:
    Apr 3, 2019
    Messages:
    65
    Likes Received:
    17
    Thanks Tim, much appreciated!
     