    Hi Team,

    I need to help figure out the "Yesterday Weather" for project. Project was not fully practicing Scrum before and I am starting next sprint. So As per my understanding Velocity will be predicated by taking Average of last three sprints. But Some sprints have no values.

    Can you please suggest what will be yesterday weather from below data.
    Sprint Commitment Completed
    1. Sprint 1 36 13
    2. Sprint 2 23 13
    3. Sprint 3 0 0
    4. Sprint 4 36 36
    5. Sprint 5 0 0
    6. Sprint 6 8 0
    7. Sprint 7 9 10
    (0+0+10)/3= 3 or (13+36+10)/3= 19.6